CHALIWASA continued with implementation of ongoing works of the phase II, which started construction during 2008, with a total cost of TZS 53.7 billion. The funding is a contribution from the Government of the Peoples’ Republic of China (TZS 5.6billion); The Bank of Arab Development in Africa (BADEA) (TZS 10.8 billion) and Water Sector Development Programme (WSDP) (TZS 37.3 billion). Phase II of Chalinze water supply covers 47 additional villages in 3 Districts namely Bagamoyo (38), Kibaha (4) and Morogoro rural (5). Due to its complexity the project was divided into 9 packages (A, B, C, D, E, F, G, H & J). Two packages i.e. Packages F and H were implemented using funds from BADEA while package J (villages in Morogoro rural including Military camps) were implemented by using grant from Chinese Government. The remaining packages (A, B, C, D, E and G) were implemented under the Water Sector Development Programme & GoT.
Current Status of package A, B, C, D, E, F, G, H and J;
1. Package F & H
On 5th November 2013, The Ministry of Water signed the contract with a new contractor M/s Badr East African Enterprises Ltd to complete the remaining works are Pressure testing Ubenazomozi – Visakazi, Ubenazomozi to Kaloleni junction, Kaloleni junction to Tukamisasa and Kaloleni junction to Lulenge elevated water tank, Landscaping and leveling at Ubenazomozi, Lulenge and Tukamisasa tank sites, The overall physical work progress is estimated to be 99.8%. This package is expected to be handed over end of June2017. However some people at Ubenazomozi, Mdaula, Matuli and Msolwa are currently receiving water from the completed works in their villages. The remaining villages that are yet to receive water are Tukamisasa, Kaloleni, Mwidu and Visakazi.
2. Package J
This package was implemented by M/S Wuhan Water Construction Engineering Company from China. However the extension of pipeline reached at 99.9% and rehabilitation of communication system is 50%. A total population of 24,925 from villages of Kidugalo, Ngerengere, Sinyaulime, Bwawani, Gwata, Kinonko and Military campus of Sangasanga, Kizuka and Kinonko will benefit from this package of which depends on package F and H.
3. Package A (Lot 1)
This package was implemented by M/S Oriental Engineering Co. Ltd from Kenya. The contract was signed on 13/8/2010 and was officially handed over on 25th March 2014 after Defect Liability Period (DFP) and the project completion is 100%. A total population of 10,912 from villages of Mihuga, Masimbani, Kweikonje, Mandamazingara, Kwasunga and Mkange are currently benefitting from this package and the project is operational.
4. Package B (Lot 2)
The implementation of Package B for the 3rd Quarter period is 100% for the original contract including additional works. This package is handed over on 07 March 2017 after the final inspection . Villages of Masuguru/Mwetemo, Kiwangwa/Mwavi, Fukayosi, Kidomole, Mkenge, Msinune, Pongwe Msungura, Madesa and Makurunge are receiving water from this package. Currently all villages receive water.
5. Package C (Lot 3)
This package is being implemented by M/S D. B Shapriya & Co from Tanzania. The contract was signed on 23/3/2011. A total population of 13,180 from villages of Kinzagu, Makombe, Talawanda, Malivundo, Msigi, Kisanga and Mindukeni will benefit from this package. The implementation of Package C is 100%. This package is handed over on March 2017. People at village of Kinzagu, Makombe, Talawanda, Msigi, Kisanga, Mindukeni and Magulumatali are currently receiving water .
6. Package D (Lot 4)
This package is implemented by M/S Building Water and Earthworks Ltd from Tanzania. The contract was signed on 13/8/2010 and was officially handed over on October 2015 and the project completion is 100%. A total population of 14,931 from villages of Chamakweza, Vigwaza, Buyuni, Mbala and Visezi are currently receiving water.
7. Package E (Lot 5)
This package is being implemented by M/S Badr East Africa Enterprises from Tanzania. The contract was signed on 13/8/2010 and was officially handed over on November 2015 and the project completion is 100%. A total population of 12,090 from villages of Chahua, Gwata, Gumba, Magindu and Lukenge are receiving water currently.
8. Package G (Lot 6)
This package is being implemented by M/S Zonghao Overseas Construction. Eng. Co. Ltd from China. The contract was signed on 13/8/2010. A total population of 13,093 from villages Kwan’gandu, Pongwekiona, Kifuleta and Kwaruhombo will benefit from the package. The implementation of package G is 100%. However completion of this package depends on completion of package F, people at villages of Kwang’andu, Pongwekiona and Pongwemnazi are receiving water currently.